Cells in at one end, tested packs off the other — one takt across both segments +86 15327155363 [email protected]

BLP-GL· Pack segment station 03 · Automated on both line grades

Liquid Cooling Plate Gluing Station BLP-GL

The adhesive nobody sees again. BLP-GL lays a thermally conductive structural bead on the liquid cooling plate and a structural sealing bead on the enclosure floor, against a stored recipe, with a record attached. Three quantities controlled; three conditions under which a part stops.

Two workpieces, one metering head Twin-servo two-component metering Record by enclosure number over PROFINET
±0.2 mmPhoto positioning
on the part as it sits
5 %Dispensed volume
per segment, live
±2 mmDispensing path
on the located part

In the line, on the fixture, with a record

The Station and Its Two Workpieces

BLP-GL is a liquid cooling plate gluing station built into the line, not a bench dispenser: it takes the part on its fixture, photographs it, dispenses against a stored recipe and hands the part on with a record attached. The same head glues both parts: the cooling plate with a thermally conductive structural adhesive, the enclosure floor with a structural and sealing bead.

Two servo-driven metering axes push the two components at a ratio between 1:1 and 2:1, set by recipe. Path speed runs up to 300 mm/s. Parameters and the pressure curve behind them go out over PROFINET, filed by enclosure number.

Process and quality engineers

Specifying a pack line for energy storage or EV pack assembly, and answerable for that bead months later.

Plant engineers replacing a hand step

A hand-dispensed bead that has started to cost at final test. The station is quoted on its own into a running segment.

BLP-GL liquid cooling plate gluing station: twin-servo metering head on its gantry above a cooling plate fixture
Station 03: fixture, camera, twin-servo metering head and mixing tube, in the line.
±0.2 mm vision±2 mm path5 % volume≤300 mm/s1:1 to 2:1 ratioPROFINET to MES
Battery pack assembly line the gluing station is quoted inside, seen along the pack segment
The pack segment it is quoted inside: plate air-tightness before it, module insertion after it.

Quoted two ways

01
Inside a battery pack assembly lineWith the stations either side of it, on one takt and one criteria sheet.
02
On its own into an existing segmentSend the two drawings; the reply says which of the two makes sense for your volume. Talk to us.

Fifteen stations · one segment

Liquid Cooling Plate Gluing Station at Station 3

The pack segment opens with enclosure and cooling-plate cleaning, then plate air-tightness, then this station, then module insertion, then module fixing. By the time the modules are in at station 4 the adhesive is structural, thermal and out of reach.

Enclosure and cooling plate arriving at station 1 for cleaning
Station 01Enclosure and cooling-plate cleaningManual
Cooling plate air-tightness test at station 2, before the gluing station
Station 02Cooling-plate air-tightnessAuto
Liquid cooling plate gluing station laying the bead at station 3
Station 03 · BLP-GLCooling-plate and enclosure-floor gluingAuto
Module insertion fixture at station 4, where modules land on the bead
Station 04Module insertionSemi-auto
Battery module being fixed in the enclosure at station 5
Station 05Module fixingManual

Before a part is allowed in

The cooling plate arrives already leak-tested at station 2: 200 kPa of dry air, held 60 s, a pressure drop of 1 kPa or less to pass. That gate sits before the glue on purpose; it is the first of the three hold conditions on this page.

Automated on both line grades

One of four automated stations in a segment that is otherwise hand work: plate air-tightness, gluing, whole-pack air-tightness and pack EOL. Automated because the thing it produces cannot be inspected afterwards, so the process record has to stand in for the inspection. The whole-pack gate later in the segment is a different test with a different threshold, written up on the pack EOL testing page.

Pack segment stationBLP-P8SBLP-P15
01 · CleaningManualManual
02 · Plate air-tightnessAutoAuto
03 · Gluing, BLP-GLAutoAuto
04 · Module insertionSemi-autoSemi-auto
05 · Module fixingManualManual
13 · Whole-pack air-tightnessAutoAuto
14 · Pack EOLAutoAuto

Both grades run the pack segment with 12 to 14 people; the four automated stations are the ones whose result cannot be checked by hand afterwards.

Hold condition 01 · the gate before the glue

Air-Tightness Before the Adhesive

A leak found on a bare plate is a plate that gets replaced. The same leak found after the bead is down is a plate with cured adhesive on it, inside a box that has already been scheduled for modules. The leak test is placed where a failed part is still cheap.

200 kPaDry air, plate pressurised
60 sHeld under pressure
≤1 kPaPressure drop to pass
Cooling plate under air-tightness test at station 2, before it reaches the liquid cooling plate gluing station
Station 02: released to gluing only when the drop over 60 s is 1 kPa or less.
Same leakFound at station 2Found after the bead
What failsA bare plateA glued plate inside a scheduled box
What it costsOne plate, swapped on the fixtureCured adhesive removed by hand, a box re-planned
Who decidesThe test, before the head movesSomeone at station 4, in a hurry
What is recordedA pass, before the glueNothing until final test finds it
Energy storage battery packs installed in a rack, where a bead laid wrong at station 3 finally shows
Where the bead is judged for real: months later, in a rack.

Same head · a different job on each part

Two Workpieces, One Metering Head

Adhesive bead path laid on a liquid cooling plate at the gluing station
One continuous bead, segment by segment, on the located plate.

The cooling plate: a thermal and mechanical interface

The bead has to be present, continuous and in the amount the thermal design assumed, because the heat path through the pack was designed on paper before anyone glued anything.

  • Large, thin, never perfectly flat, and delivered with its own supplier's tolerances.
  • Located to 0.2 mm, so the path runs on the plate that is on the fixture rather than on the nominal one.
  • Volume judged per segment, live, so a corner and a long straight each get the quantity the design assumed.
Thermally conductive structural adhesive

The enclosure floor: a structural and sealing bead

Continuity along a defined path carries as much weight as total quantity. Enclosures are fabrications, and between batches the floor is the least repeatable surface this station touches.

  • Path committed to 2 mm on the located part, written as a promise about where the bead lands.
  • Segment volumes follow the flange run, the corners and the long straights of the floor.
  • Out of reach once module insertion starts at station 4; the record is the inspection.
Structural and sealing adhesive
Structural sealing bead along the floor of a battery pack enclosure
The floor bead follows its defined path around the flange before the modules go in.
S01Flange runCommanded volume
S02CornerCommanded volume
S03Plate face, long straightCommanded volume
S04CornerCommanded volume
S05Plate face, long straightCommanded volume
S06End runCommanded volume
A path is not one number. It is a sequence of segments, each with its own commanded volume. Change the part and the segments change; the metering behind them does not. Blueprint pack and module dimensions are on the energy storage pack line page.

Position · volume · time

Three Controlled Variables, Three Hold Conditions

Measured, commanded, clocked. Right place with the wrong quantity, or right quantity left open too long: neither reaches station 4.

Vision head locating a part on its fixture before the dispensing head moves
Measured

Position

±0.2 mm

Vision locates the part as it sits on the fixture, before the head moves.

Held upstream: a plate that failed the station 2 gate never reaches the camera.
Liquid cooling plate gluing station metering head commanding volume segment by segment
Commanded

Volume

5 %

Dispensed against commanded, per segment, judged live.

Held: the live pressure curve leaves the window stored in the recipe.
Module conveyor buffer between the gluing station and module insertion, where open time runs
Clocked

Time

Open time

Stored with the adhesive recipe; starts when the bead is finished, stops when the modules go in.

Held: open time expires before module insertion at station 4.

Six figures · what each governs · when it is judged

Liquid Cooling Plate Gluing Station Figures

Two describe geometry, the rest describe substance and evidence. The pair most often asked about is 0.2 mm and 2 mm, and the gap between them is the point: the station measures the part to 0.2 mm so that a 2 mm path can be a promise about the bead instead of a hope about the fixture.

FigureWhat it governsWhen it is judged
±0.2 mmPhoto positioningGeometryWhere the station believes the part is, against the part on the fixture, not the nominal one.Every part, before the head moves.
±2 mmDispensing pathGeometryWhere the bead is committed to land on that located part. A commitment to your bead design, not the camera's error.Every bead, on the located part.
5 %Dispensed volumeHow much adhesive went down against how much was commanded for that segment.Live, on every segment of every bead.
300 mm/sPath speed, up toThe travel envelope the path is planned inside; the figure your cycle time is calculated from.Set by recipe.
1:1 to 2:1Mix ratio, settableThe two-component ratio the twin-servo head holds.Set by recipe with the adhesive, fixed for the run.
PROFINETTo MES, by enclosure numberWhere the parameters and the pressure curve go.At acceptance, against the criteria sheet both sides sign.
Battery module that lands on the bead at station 4, after which the figures are the only inspection
The module that lands on the bead at station 4. From then on the record is the only inspection there is.
Measure to 0.2, promise 2The camera's figure buys the bead's figure. Neither is the other's error.

Hold condition 02 · the pressure window

Volume as the Controlled Variable

This is the mechanism the rest of the station is built around. What gets commanded is volume: not a dispense time, not a head pressure, not a number of seconds an operator learned to trust.

Each segment of the path carries a commanded quantity from the recipe for that part number, and dispensed volume is held to 5 percent against that command.

Pressure is what proves it. The head records a live pressure curve while the bead is laid, and the recipe carries the window that curve has to stay inside. A blockage, an air inclusion, a cartridge running down or a mixing tube starting to set all have a shape in that curve before they have a shape you could see on the part.

The station has already decidedWhen the curve leaves its window, the part is held. Not released to station 4, and not passed on with a note for someone to look at later.
Twin-servo two-component metering head with its static mixing tube at the liquid cooling plate gluing station
Two components at the recipe ratio, one mixing tube, a pressure transducer behind the nozzle.
01

Operator

Selects the recipe that matches the part, releases parts that passed, handles parts the station held.

Does not write or edit the recipe.
02

Process engineer

Reads the curve, decides what the held part gets, and signs that decision into the record against the enclosure number.

Does not release a held part on a verbal.
03

Quality engineer

Sees the criteria the window came from, written before the line shipped and signed by both sides.

Does not meet the window for the first time at acceptance.
One suspect pack stays one suspect packCurve, commanded volume, delivered volume and recipe number are filed against that enclosure number. A per-part answer instead of a per-shift argument, which is what a bad hour here usually costs.

What a hold looks like on the floor

The part stays on its fixture; the screen shows the recipe, the segment and the curve against its window. The process engineer's disposition and any rework go into the record.

Drawings, adhesive, target takt

Two Drawings, One Adhesive, One Takt

Send the enclosure drawing, the cooling-plate drawing, the adhesive you intend to use with its mix ratio, and the takt you are building to. That is enough to say how this station would be configured for your pack and what it would be quoted as inside the segment.

01Enclosure drawing 02Cooling-plate drawing 03Adhesive and mix ratio 04Target takt

Hold condition 03 · the clock in the machine

Open Time on a Clock

Adhesive has a working life once it is mixed and laid, and the pack segment has a buffer, a break, a stopped conveyor and a module that was not ready. Those two facts collide at station 4, and this station is where the collision is managed.

Open time is stored with the adhesive recipe. The clock starts when the bead on that part is finished and runs until the modules go in. If it expires, the part is held.

Module insertion at station 4, where the open-time clock stops when the modules land on the bead
Station 4: the clock stops when the modules go in.

A stored timer does not get busy

Shift discipline works on a normal day and fails on the day the line stops, because that is the day everyone is busy with the line. The clock is in the machine for that reason.

01

Bead not yet cured

The plate or enclosure is cleaned off and re-glued at the station. The process engineer judges that call and records it.

Recorded against the enclosure number
02

Bead already cured

The held part goes to the rework position, the adhesive is removed by hand, and the part re-enters the station as a fresh part.

A part that went round twice is visible as one
Static mixing tube on the twin-servo two-component metering head, changed in line
The mixing tube on the twin-servo head: the consumable that makes a stoppage recoverable.

The stoppage that has to be recoverable

Mixing Tube Changed In Line

A two-component adhesive begins to set inside the mixer as soon as the head stops. The mixing tube is changed in line, without taking the station out of the segment, so a stoppage becomes a tube change rather than a queue of held parts.

01The line stopsBuffer, break or a module not ready: the head stops, the clock keeps running on the glued part.
02Tube changed in lineThe static mixer is swapped at the head; the station stays in the segment, the recipe stays loaded.
03A fresh first beadLaid against the same window and the same commanded volumes, recorded like any other.
1:1 to 2:1 by recipeTwin-servo meteringMixer changed in line
Recipe · this enclosure, this cooling plateFiled by part number
01Bead path
Taken from your drawings
02Segment volumes
One command per segment
03Pressure window
Per adhesive, signed by quality
04Mix ratio
1:1 to 2:1, fixed for the run
05Path speed
Up to 300 mm/s
06Open time
Per adhesive, timed by enclosure number
Written by the process engineer · signed by quality · selected by the operator

Every number lives in a recipe

Recipes Held by Part Number

Operators select recipes. They do not write or edit them. That is a deliberate restriction, the same one placed on module pressing and on busbar welding, because a line where three shifts can each nudge a parameter is a line where nobody can explain a bad month.

ChooseThe recipe that matches the part number on the fixture.
ReleaseParts that passed: curve in window, volumes held, clock not expired.
Handle heldParts the station stopped, with the process engineer's disposition.

Training follows those lines after site acceptance: operators, process engineers and maintenance separately, because the three need different things from this station. The same metering control runs on the smaller dispensing machine on the cylindrical and consumer pack lines, worth knowing if you build both kinds of pack in one plant.

Process engineering floor where the gluing station recipes are written and signed off
Where the recipe is written: the process engineers who own the parameter, with quality signing beside them.
Written once, signed onceWritten by the process engineer who owns the parameter, signed off by quality, criteria agreed in writing before the line ships.

Three trainings, not one

01
OperatorsChoose, release, handle held. Nothing on the recipe screen.
02
Process engineersThe recipe fields, the window, the disposition of a held part.
03
MaintenanceThe metering axes, the mixing tube change, the pressure transducer.

PROFINET · filed by enclosure number

The Record That Leaves the Station

Over PROFINET, filed by enclosure number, the station hands your MES five things. The set is chosen so it can answer the questions that get asked after the fact.

What leaves the stationThe question it answers
The recipe number it ranWhich recipe was this part built to
Commanded and delivered volume, per segmentHow much adhesive actually went down
The pressure curve behind the beadWhat the pressure was doing at the moment it went down
The open-time stampsHow long the bead was open before modules landed on it
Any hold event, with disposition and rework recordWhether this part had been round the station before
Acceptance bench where the gluing station record fields are checked against the signed criteria sheet
The record fields are read back against the criteria sheet before the line ships.

The interface and the data are provided

Mapping them into your MES is a scoped piece of work agreed with your automation and IT people during the project, said plainly rather than letting a protocol name stand in for an integration. What is not negotiable is that the data exists and leaves the station.

Pack end-of-line test station that reads the same enclosure number the gluing record was filed under
Pack EOL at station 14 reads the same enclosure number.
The only form the evidence survives inOn this station the bead cannot be inspected afterwards. The record is not a convenience. It is the inspection.
Filed by
Enclosure number
Leaves over
PROFINET
Read by
Your MES, and pack EOL at station 14
Mapped by
Your automation and IT people, scoped in the project

A format change reaches this station as three things

A New Enclosure, a New Path

A new bead pathFrom your new drawings: which face, which route, where the flange run starts and ends.
New fixturingTo present the part to the camera and the head, with its vision model.
New segment volumesAlong that path, with the open time for the adhesive.
≤2 hInsertion and fixing tooling changed over, inside the compatibility envelope
1 shiftA first-time format: tooling, dispensing path and air-tightness criteria together, first-article qualification at the end
Fixtures for the pack compatibility envelope, changed over when a new enclosure reaches the gluing station
The part changes; the camera and the head are presented to it the same way.
Prismatic cells whose format sets the module, the enclosure and the bead path at the liquid cooling plate gluing station
A new cell format arrives here as a new enclosure floor and a new path. The capability set stays where it is.

What does not move

  • The 0.2 mm photo positioning.
  • The 2 mm path commitment on the located part.
  • The 5 percent volume accuracy, per segment.
  • The record that goes out over PROFINET.

These describe the station, not the last part it ran. What a change of cell, module or pack costs across the whole line is on the compatibility and changeover page.

Engineered, not configuredThe capability set is fixed; the recipe is what changes. That distinction is worth settling in writing before anyone signs.

Every figure becomes a line on a criteria sheet

The Liquid Cooling Plate Gluing Station at Acceptance

The engineer who set the parameter writes the criterion and quality signs it, before the line ships, so nobody arrives at acceptance arguing about what the number meant.

Prebuild bay where the pack segment runs works acceptance with the customer's enclosures and cooling plates

FATWorks acceptance, in a prebuild bay

The segment runs with your enclosures and cooling plates, and the sampled packs are built with the recipe this station will run in your plant.

  • Recipes called by part number, not typed in.
  • Volumes held to 5 percent, segment by segment.
  • Pressure curves in window, and hold events behaving as written.
Pack segment running continuously at takt during site acceptance, downstream of the gluing station

SATSite acceptance, at takt

Continuous running at takt in your plant, with your own parts and adhesive, against the same criteria.

  • Open time timed on the live line, with its buffers and breaks.
  • Record fields arriving in your MES by enclosure number.
  • Operators, process engineers and maintenance trained separately after the run.
01
Recorded line by lineStation, measured value and criterion side by side.
02
The owner corrects itThe engineer who owns that criterion makes the change, not whoever is nearest.
03
Only the misses are retestedEverything that passed stays passed.

What to send

Drawings, Adhesive, Target Takt

The two drawings say where the bead runs, on which face, and whether one station has to serve both parts on your line. Add the adhesive with its mix ratio and the takt you are building to, and the reply describes the liquid cooling plate gluing station you would actually be buying, not the one in the datasheet.

01
Enclosure drawingFloor face, flange, and the path the sealing bead has to follow.
02
Cooling-plate drawingPlate outline, ports, and the face the thermal bead goes on.
03
Adhesive and mix ratioThe two-component system you intend to run, anywhere from 1:1 to 2:1.
04
Target taktThe cycle the path speed and the segment count are planned against.
Battery pack enclosure with its lid: the two parts the enclosure drawing and the cooling-plate drawing describe
The enclosure the drawings describe: floor, flange and the plate that sits on the bead.
24 hoursReply time on the two drawings: configuration, segment count, and the record fields your MES would receive.

If the volume does not justify it

If your volume genuinely does not justify an automated station, the reply says so, and you still get the criteria you should be holding a hand-dispensed step to.

How to reach you

[email protected]

Start with the two drawings

Send the Two Drawings

Four inputs to our engineering team and the configuration, the segment count and the record fields come back within 24 hours. Behind it: 26 engineers and 40+ line segments into 12 countries, on the about page.

Phone / WhatsApp
Address
Wuhan, Hubei, China
Response
Within 24 hours