Cells in at one end, tested packs off the other — one takt across both segments +86 15327155363 [email protected]
Battery module and pack assembly line standing along its full run under studio light

About BatteryLine Pro

Battery Assembly Line Manufacturer for Module and Pack Plants

One part of the battery industry: the plant floor between a pallet of finished cells and a tested pack on its way out. The layout is drawn to your building, most of the machines standing on it are designed and built in our own hall, and the line is signed off station by station against criteria written before anything ships.

LedgerSince 2016

Company ledger

Assembly equipment since
2016
Turnkey lines since
2019
Engineers
26
Assembly hall
6,000 m²
Full-line pre-assembly bays
3
Line segments delivered
40+
Countries shipped to
12

Every figure on this page is attached to a way of measuring it, agreed before the line runs.

What this company is

The Company Behind the Lines

Module and pack assembly lines for plants that receive finished cells and ship tested packs. Three tiers run at 4 to 8, 8, and 12 to 15 PPM, each laid out against the building it will stand in rather than against a standard drawing.

Nine of the workstations on those lines are our own designs, drawn, built and powered up in our own hall before they ship. That one fact is behind most of what we can do and a reseller cannot: a layout redrawn to your column grid, an envelope checked against your cell the same day, and acceptance criteria written by the engineers who set the machine parameters.

17 / 15Module stations and pack stations quoted against
≥99%Equipment-caused yield, human factors excluded
≥1000 NBusbar joint strength, proved on your material
3 certsISO 9001, CE and RoHS held
Aerial view of the BatteryLine Pro plant: two assembly halls and the engineering office block where module and pack lines are built and powered up before shipment
The plant campus: two assembly halls where the nine workstations are built and powered up before shipment, with the engineering office in front.
26 engineers, 32 stationsA narrow scope is what lets one engineering team own every station on the line.

Where we sit

Our Place in the Battery Chain

Equipment since 2016, complete turnkey lines since 2019. Those two dates matter more than a founding year: the first years were single machines dropped into other people’s lines, which is where the station-level parameters came from, and the turnkey work since taught us to hold a takt across 32 stations rather than at one.

Prismatic lithium cells arriving as finished goods on a tray
Upstream

Cell manufacturing

Mixing through to formation is a different class of equipment in a different building. Cells arrive here finished, on a tray, with a code on them.

Cell unloading and sorting section at the head of a battery module line
This company

Module and pack assembly

Thirty-two stations between the incoming tray and line-off. Layout, machines, commissioning and the acceptance set all come from one engineering team.

Finished battery pack leaving the line with its test record attached
Downstream

Your own customer

The integrator or vehicle maker who receives the pack and asks for its test record. What they ask for is what the end-of-line gate has to produce.

What has shipped

Delivered Record and Three Ways to Buy

40+Line segments delivered, counting complete lines and segment rebuilds together
12Countries those segments were shipped into and commissioned in
32Stations in the sequence every layout, quotation and acceptance set is built on

Segments rather than lines is the honest unit, because much of the work is one part of an existing plant: a module segment holding back a pack segment that was already sized correctly. Three ways to buy come out of the same catalogue and the same engineers.

A complete line

One project, one layout, one acceptance plan covering both segments.

A single workstation

One machine dropped into a line you already run, quoted against the part it handles.

A segment rebuild

One segment replaced while the rest of the plant keeps running.

2016 → 2019

Single machines into other people’s lines for three years, then complete lines. The first period is where every station-level parameter came from.

Supply scope

Scope From Cell Arrival to Line-Off

Four segments, and every station we sell sits inside them.

Prismatic cells being taken off the incoming tray for scanning and sorting
01 · Cell handling

Off the tray, scanned, sorted

Cells come off the incoming tray, each one is scanned and tested, and a rejected cell leaves a gap that is refilled before the group moves on.

Battery module with busbars welded across its terminals
02 · Module segment

Grouped to finished module

Grouping, cleaning, taping, stacking, pressing, addressing, welding and testing, until a finished module comes off the end.

Battery pack enclosure with cooling plate and modules before the cover goes on
03 · Pack segment

Enclosure to closed pack

Enclosure and cooling plate loading, gluing, module insertion and fixing, wiring, closing and testing.

Tested battery pack released at line-off with its record attached
04 · Line-off

Released with its record

The pack is released with its test record attached to it, which is the document your own customer will ask you for.

Inside our scope

Cell handling, module assembly, pack assembly and line-off — the four segments above, on all three tiers. Both halves are written up in full on the battery module assembly line and battery pack assembly line pages.

Outside it

Cell making from mixing through to formation, formation and grading, electrolyte filling, and container integration. Different equipment, different building, somebody else’s engineering.

Holding a narrow scope is a design decision. The engineer who sets a press force knows what the welder downstream needs from the stack, and whoever writes the acceptance criterion for module testing has commissioned the sorting station that fed it.

Who we build for

Buyers We Build Lines For

Five groups, and the difference between them is which input is already fixed before the layout starts.

Commercial and industrial storage battery pack ready for line-off

C&I storage pack plants

A pack count per project high enough that takt and headcount decide the business case, usually with the cell already chosen.

Fixed first
Cell
Liquid-cooled grid-scale storage pack built for containerised systems

Grid-scale integrators

A containerised system design, liquid cooling, and a pack drawing fixed by the project rather than by them.

Fixed first
Pack drawing
Prismatic cells of the size used in residential storage packs

Residential storage makers

Five to 30 kWh, air cooling, and a cost target that normally lands on the semi-automatic tier.

Fixed first
Cost target
Battery module drawing of the kind an EV pack supplier receives from its customer

EV module and pack suppliers

A pack drawing fixed by their customer and a takt fixed by the vehicle line, so the layout bends rather than the takt.

Fixed first
Takt
Gantry laser welder of the type bought on its own to clear a welding bottleneck

Plants already running a line

Arrives as a bottleneck rather than a project: a hand-welding step that cannot hold takt, a missing test gate, a gluing station setting the pace for everything behind it.

Fixed first
The building

How a project opens

Five Documents In, Three Back

Cell datasheet

Format and dimensions with tolerances, so the gripper and fixture question is answered on day one

Module configuration

Series and parallel count, which sets the stack, the press length and the busbar pattern

Pack drawing

Enclosure, cooling plate and interfaces, which decide the gluing path and the pack station count

Target takt

PPM, or annual output we can convert into one, which picks the tier

Floor plan

Clear height, floor loading and utility entry points, marked on the plan of the bay itself

Back within 24 hours: a tier recommendation with the reason behind it, a layout drawn against that floor plan, and the labelled station list for both segments.

Our own designs

Nine Workstations of Our Own Design

Nine workstations on a BatteryLine Pro line are our drawings rather than bought-in machines with our plate on them. What that ownership buys you is written under each one.

BLP-UL cell tray unloading station with six-axis robot and vision
BLP-UL

Cell tray unloading

Grippers drawn around your tray pitch and cell face, five cells to a pick.

BLP-CS cell scanning, testing and sorting station with reject lane
BLP-CS

Cell testing and sorting

Reject and refill logic set by us, so a gap never travels downstream into a group.

BLP-SP module stacking and pressing station under servo force control
BLP-SP

Stacking and pressing

Force read through the stroke rather than sampled at the end of it.

BLP-AD terminal addressing and polarity reading station
BLP-AD

Terminal addressing

One vision set locates the terminal and reads its polarity in the same look.

BLP-W6 in-line busbar laser welding station with 6 kW source
BLP-W6

In-line busbar welding

Recipes stored per busbar geometry and called by the part that arrives.

BLP-EOL module end-of-line testing station
BLP-EOL

Module end-of-line testing

Thresholds written by the group that owns the test physics, not by a salesman.

BLP-GL cooling plate and enclosure adhesive dispensing station
BLP-GL

Cooling plate gluing

Bead path and metered volume, with the curves handed up to your MES.

BLP-CV conveyor carrying battery modules and fixtures between stations
BLP-CV

Module conveying

Stop and lift units positioned for the station in front of them. It carries modules and their fixtures, including the handover into the pack segment, and never finished packs.

BLP-WG off-line four-axis gantry laser welding machine
BLP-WG

Off-line gantry welding

Four-axis welding kept off the takt, so the line never waits for it.

ISO 9001 CE RoHS Nine stations, our own drawings

Who draws and who travels

Twenty-Six Engineers, Four Disciplines

Almost a third of the team spends its year on other people’s floors, and what they bring back is what the mechanical group redraws. Field commissioning is a permanent group here, not a role a sales engineer picks up when a shipment lands.

DisciplineWhat it ownsEngineers
MechanicalLayout, frames, grippers, fixtures8
Electrical and controlTest stations, controllers, remote diagnostics6
Laser and vision processWeld recipes, addressing, inspection thresholds4
Field commissioningInstallation, acceptance, operator training8
BatteryLine Pro engineering team of mechanical, electrical, laser and vision and field commissioning engineers in front of a battery module assembly line
Engineers from the four disciplines on the pre-assembly floor: the people who draw the layout, set the machine parameters and sign the acceptance plan.
8 of 26 travelThe commissioning group that signs your acceptance plan is the same group that stood the line up in the pre-assembly bay.

Before a crate is closed

Three Full-Line Pre-Assembly Bays

The machines are built in a 6,000 square metre hall, and three of its bays are reserved for something most equipment suppliers have no use for. A complete line is stood up in the bay in its shipping configuration, powered up, and run before a single crate is closed.

  • Faults that only appear when 32 stations share a controller are found in our building rather than in yours.
  • The commissioning engineers arrive at your plant having already seen this specific line running.
  • A supplier that buys its stations in has nothing to pre-assemble, because it does not own the mechanical design that makes the stations index to each other.

When the line runs in your plant for the first time, it is the second time it has run — which is why we accept being measured on how a line behaves at start-up, not only on how each machine behaves alone.

Complete battery assembly line standing powered up in a pre-assembly bay before crating
A complete line erected in a pre-assembly bay, powered up and run in its shipping configuration.
IndexingStations indexed against each other in the positions they will ship in
TransferConveyor stops and lifts set for every station in front of them
VisionCameras taught on the parts they will actually see
InstrumentsTest instruments proved against a known reference

Ownership of the numbers

Envelopes and Acceptance Criteria

The compatibility envelopes we quote are ours to set, and that is a different thing from knowing them.

What is boundedEnvelope
Cell100–220 mm wide × 100–220 mm high × 20–80 mm thick
Module400–1200 × 100–300 × 100–250 mm
Press length, BLP-SP300–1100 mm

Those numbers exist because our mechanical group drew the grippers, fixtures and addressing programmes that produce them. So when a cell lands 5 mm outside an envelope, the question is not whether it fits: it is which fixtures and programmes change, who changes them, and whether the takt moves. Four items follow the part and four do not, and the split is on the battery module assembly line page.

Changeover fixtures and grippers racked beside a module station
The changeover fixtures that make an envelope a number rather than a hope.

One author, three documents

Layout, station list and acceptance set come from one party here. The engineers who set the press force and the weld recipe also write the criterion each station is signed off against, and they sign their own work at your site.

Three authors, three documents

Where those three documents come from different suppliers, the criteria drift toward what each machine can prove about itself rather than what the line has to deliver at the end of a shift. The acceptance page covers how they are agreed.

What a line is made of

Five Technologies a Line Is Built From

Each discipline owns its own stations, its own parameters and the criteria those stations are accepted against.

Laser welding head over a battery module busbar
01

Laser process

A 6 kW source welding busbars in line on BLP-W6, with BLP-WG covering off-line work.

Wavelength
1070 nm
Power
1000–6000 W
Stability
3%
Six-axis robot with vision picking cells from a tray
02

Vision and robotics

BLP-UL picks five cells at a time; BLP-AD locates the terminal and reads polarity.

Payload
220 kg
Reach
≥2650 mm
Addressing
≤0.2 mm
Servo press closing on a stacked battery module
03

Servo force and metering

BLP-SP reads force through the stroke; BLP-GL meters adhesive volume and holds the bead path.

Press force
0–8000 N
Bead path
±2 mm
Volume
5%
End-of-line electrical test station with insulation and hipot instruments
04

Electrical test

BLP-CS measures every incoming cell; BLP-EOL runs insulation and hipot on every finished module.

Insulation
DC 1000 V
Floor
≥500 MΩ
Hipot
DC 2800 V
Module conveyor with modular stop and lift units between stations
05

Transfer and fixturing

BLP-CV decides whether the other four hold their numbers, by locating each module for the station in front of it.

Load
≥200 kg
Speed
≤20 m/min
Carries
Modules

Send the drawings

Send Your Cell and Pack Drawings

A tier recommendation, a layout drawn to your floor plan and a labelled station list come back within 24 hours.

Cell datasheet Module configuration Pack drawing Target takt Floor plan

The irreversible station

Three Rules That Lock a Weld Recipe

Busbar welding is the one station on a module line whose output cannot be undone. Three rules hold it, and all three are enforced by the machine rather than promised in a document.

In-line busbar laser welding station with post-weld inspection immediately behind it
BLP-W6, with the post-weld inspection station reading penetration and bead width directly behind the welder.
Welded busbar and terminal sample coupons clamped in a tensile pull test fixture
Sample coupons in the pull-test fixture, kept with the recipe they locked.
01

A recipe belongs to a geometry, not a shift

Parameters are stored per busbar geometry and called by the part that arrives at the station. A geometry with no locked recipe does not run: the station refuses it. That is an interlock, and it is the reason a new busbar variant cannot quietly enter production on yesterday’s settings.

02

A recipe earns its lock on your material

Pull testing destroys the joint it tests, so it can never be performed on a production module. Parameters are proved on sample joints made from your own busbar and terminal material, pulled until the 1000 N floor is met with margin, and the power, speed, focus and beam pattern that produced those samples are locked for that geometry.

Production joints are then judged on the two measurements that survive the part: penetration of 1.0 mm or more and bead width of 1.5 mm or more, read at the post-weld inspection station immediately behind the welder.

03

The operator does not hold the recipe

Weld parameters are not adjustable from the station in production, because a joint welded on adjusted parameters no longer matches the sample the criterion was proved against. Where a line lets a shift leader tune power to clear a backlog, every joint made that afternoon has left the evidence chain, and nobody finds out until resistance climbs in the field months later.

  • The locked recipe for each busbar geometry
  • The sample pull-test results it was proved against
  • Penetration and bead width for every production joint

A joint outside either measurement is marked at inspection and the module leaves the flow before manual re-inspection and module end-of-line testing, carrying the station’s record of what it found. The rework decision on your side is then made against a measurement rather than an opinion. The station itself is on the busbar welding station page.

The unit of description

Two Station Sequences We Quote Against

17
Module stations
15
Pack stations

A layout, an equipment list, a headcount and an acceptance set are all built on the same 32 stations, so a change to any one of them is visible in the other three.

Cell taping station inside the seventeen-station module sequence
One of the seventeen module stations, labelled and priced in the same list your operators will work from.

Every station in both sequences is labelled AUTO, SEMI-AUTO or MANUAL, and the labelled list is in your hands before anything is signed rather than discovered during commissioning. The labelling is done by the commissioning group, who are the people who will stand at those stations with your operators, and it is not adjusted to make a quotation read better.

AUTO

Runs inside the takt with no operator standing at the station.

SEMI-AUTO

Machine cycle, operator loads or unloads. Counted in the headcount.

MANUAL

Done by people. Most of the pack segment sits here on every tier.

The sentence most suppliers avoid

The Manual Shape of Pack Assembly

Applied honestly, that labelling discipline produces a sentence most equipment suppliers would rather not write: the pack segment is predominantly manual on every tier. The standard tier carries a single automatic station in that segment, enclosure floor gluing.

  1. Module insertion and fixing
  2. Series copper busbar installation
  3. BMS installation
  4. MSD and connector installation
  5. Harness dressing
  6. Cover installation and tightening
  7. Front panel installation

Why it stays manual

Each of those steps changes shape with the pack variant: a different harness route, a bracket moved, a connector repositioned. Automating them means dedicated tooling per variant, written off the day that variant is superseded, while 12 to 14 people absorb a drawing change on the day it lands.

Why the headcount is quoted

Those figures appear in the quotation next to the equipment figure, because they set your shift roster and your labour cost for as long as the line runs. A quotation describing the same pack segment as fully automatic is describing tooling that does not yet exist for your variant list.

Battery pack enclosure open at the cover installation step of the pack segment
TierCellsModulePack
BLP-P8S4412–14
BLP-P154312–14

How the numbers work out against a target output is on the battery pack assembly line page.

How each number is tested

Figures Tied to a Measurement

Every figure this company publishes is attached to a method for measuring it, and the method is agreed before the line runs rather than argued about afterwards.

FigureHow it is measuredAgreed
8 PPM taktUtilisation means time utilisation multiplied by performance utilisation multiplied by first-pass yield, so both sides measure the same takt on the day it is verified.In the acceptance plan
≥99% yieldEquipment causes alone, with human factors excluded. First-pass yield is input quantity minus NG units divided by input quantity, and what counts as an equipment cause is agreed station by station in writing.Before the acceptance run
≥1000 N jointProved on your busbar and your terminal, on sample joints made during commissioning. Those samples are kept with the recipe they locked.At recipe lock
≥99.9% scanApplies to readable incoming codes. Unreadable incoming labelling sits outside it, because a scanner cannot be held responsible for a code that was never printed properly.In the acceptance plan
4 m clear heightMeasured under the lowest obstruction over the line run, not to the roof. Floor loading of 800 kg per square metre or more is a design input rather than a preference.At layout

A yield percentage quoted without that definition cannot be tested, because every disputed unit becomes an argument about attribution. Voltage and resistance accuracies are instrument specifications, testable on acceptance day against your own reference cell.

How the work is controlled

Quality System and Certification Scope

ISO 9001Governs who sets a criterion, who checks it, and how a deviation is escalated instead of absorbed.
CECovers the equipment as shipped, so the machines can enter the markets our customers sell into.
RoHSApplies to the materials in the machines themselves, declared at shipment.

Underneath the certificates the arrangement is simple. Criteria for each station are set by the discipline that owns the physics of that station, and a deviation found at commissioning goes back to whoever wrote the criterion. It is either defended with evidence or changed on paper before the line is signed off.

  • Laser and vision process owns the welder and the addressing station
  • Electrical and control owns the test stations
  • Mechanical owns the press and the conveyor

Available before commitment

Four Documents Before Commitment

Four documents are available to you before any commitment, and all four are the ones the line is later measured against.

The layout

Drawn to your building and your column grid, not to a standard drawing

The station list

Both segments, every station labelled AUTO, SEMI-AUTO or MANUAL

The test item list

What end-of-line measures on a module and on a pack

The acceptance criteria

The threshold each station is signed off against, station by station

Named groups, not promises

Responsibility From Enquiry to Acceptance

A turnkey order covers layout design, equipment, installation, commissioning, acceptance and operator training. Each of those has a named group behind it.

Line layout drawing spread on a desk beside a floor plan and scale rule
The layout stage: line run, station spacing, operator positions and utility entry drawn onto your floor plan.
Acceptance instrument cart and record station at the end of a commissioned line
The acceptance stage: instruments, the test programme and the record, run on parts you supply.
01 · Mechanical with electrical and control

Layout drawn to your floor plan

Line run, station spacing, material entry and exit, where operators stand, and where power, compressed air and nitrogen enter the building. The 8 mechanical engineers who draw it are the same people who drew the stations standing on it, so a column in the wrong place is a layout problem rather than a machine problem.

02 · Assembly hall

Build and pre-assembly

Machines are built in the hall, then the complete line is stood up and run in a pre-assembly bay before shipment, in the configuration it will ship in.

03 · Field commissioning

Installation and commissioning

Carried out by the field commissioning group. How many of those 8 engineers attend, and which disciplines travel with them, is written into the acceptance plan before shipment rather than decided when the crates land.

04 · Both sides sign

Acceptance on your materials

Station by station against the criteria agreed beforehand, on cells, busbars, end plates, enclosures and cooling plates from your own supply chain — a line accepted on our sample parts has proved nothing about yours. We provide the test programme, the recording and the engineers, and both sides sign the same document. The acceptance page covers the sequence and what happens if a criterion is missed first time.

After the line is signed

Training, Spares and Remote Diagnostics

Training is delivered on your line, to the people who hold the shift, and concentrates on the three things that decide whether it still performs as accepted a year later.

  • Recipe management on the welding station
  • Criteria setting on the sorting and end-of-line test stations
  • Fixture changeover inside the envelope
48 hWear parts dispatched within 48 hours of an order
RemoteDiagnostics built into the line, held by electrical and control
Wear part spares case beside a remote diagnostics control cabinet
The spares set and the diagnostics gateway that stay with the line after handover.

A controller or vision fault can be looked at by the engineer who commissioned it before anyone books a flight. The electrical and control group holds that connection, which is why a diagnosis usually starts from the parameters as they were left at acceptance rather than from a description over the phone.

How to reach you

[email protected]

Start a project

Start a Line Project

For a complete line, send the cell datasheet, module configuration, pack or enclosure drawing, target takt and floor plan, and a tier recommendation, layout and labelled station list come back within 24 hours. For a single station, send the drawing of the part it handles and the takt it has to hold.

Phone / WhatsApp
Address
Wuhan, Hubei, China
Response
Reply within 24 hours

Both routes reach the engineering team through the contact page.